3 week look ahead 7/21
Week of 7/21/25 : level #2 kitchen cabinets installation
Level #2 & #1 tile install
Level #2 install unit doors & trim
Fire tape level #3
Deliveries : doors ,trim ,tile
Electrical - feeds to ruts
Week of 7/28/25 : level #2 kitchen cabinets installation / template countertops level #2
Tile - level #2  install
Level #1 kitchen cabinets installation
Level #2 trim
Level #3 sprinkler and rough frame inspection
Level #3 insulation
Week of 8/4/25 level #1 kitchen cabinets installation
Level #1 tile installation
Level #1 unit door install & trim
Level #3 load / hang sheet rock