3 week look ahead 7/21

Week of 7/21/25 : level #2 kitchen cabinets installation
                               Level #2 & #1 tile install
                               Level #2 install unit doors & trim
                               Fire tape level #3
                               Deliveries : doors ,trim ,tile
                               Electrical - feeds to ruts
Week of 7/28/25 : level #2 kitchen cabinets installation / template countertops level #2
                                Tile - level #2 &#1 install
                                Level #1 kitchen cabinets installation
                                Level #2 trim
                                Level #3 sprinkler and rough frame inspection
                                Level #3 insulation
Week of 8/4/25 level #1 kitchen cabinets installation
                            Level #1 tile installation
                            Level #1 unit door install & trim
                            Level #3 load / hang sheet rock