3 week look ahead 4/7

Week of 4/7/25:

Siding - siding, decking, rails
Sprinkler - level #3 dry system mains, deliver laterals Wednesday - start installing
HVAC - level #1 & #3 bath exhaust fans, level #2 & 1 cassettes and rooftop equipment pending approval of price
Plumbing -roof penetrations weather permitting, level #1 rough drops through sod ,
Electrical - Run unit power feeds to rtu’s , level #1 roughs / possible start on switch gear
Frame - Exterior decks at units #106 & #107 ( materials delivered to site                   
Steel- install added beams at garage for new posts at units #101,#201,#108 , #208
Framers - added walls and posts at units #101,201,108,208
Fire stopping - start fire caulking level #2 then down to #1
 
Week of 4/14/25:

Siding - Exterior decks, siding and rails - ongoing
Sprinkler - level #3 dry And wet
HVAC -rough inspection level #1 &#2, set rooftop rtu’s, install common hallway cassettes
Electrical - switch gear,power feeds to RTU’s , possible start BDA design & install, end at Level #2 2 hour rated closet at trash room
Plumbing - level#1 rough inspection,set tubs, shower pans level #1 &#2
Fire stopping - Level #1
Building inspection level #2 , start level #2 insulation level

Week of 4/21/25:

level #2  insulation
Siding, trim, deck & rails
Sprinkler : level #3 dry and wet systems
HVAC  - RTU’s ,pitch pockets , interior cassettes ,exterior wall caps
Electrical - switch gear, bda, RTU’s
Plumbing - set tubs, showers ,valves
Fire stopping - level #3 & garage