3 week look ahead 4/21
Week of 4/21/25:
level #2 Insulation start
Siding - Exterior decks, trim, siding
Sprinkler - Level #3 dry system laterals
HVAC - Ruts, pitch pockets, line sets, cassettes
Electrical - Level #1 rough electrical inspection 4/22/25 at 10 am, feeds to roof, start switch gear
Plumbing - Tub and shower sets pending west view labor to prep areas, tub and shower valves, vents to roof
Firestopping - Resume fire caulking level #1 & #3
3rd delivery kitchen / bath cabinets
Store fronts - deliver/install
Week of 4/28/25:
Level #2 building inspection pending rough plumbing inspection
Insulation level #2 & inspect
Level #1 rough frame inspect & insulate & inspect
Level #2 Sheetrock & tape
Siding - Decks, rail, side
Sprinkler - Level #3 dry & wet systems
HVAC - Ruts, cassettes, mechanical cleats pending CO
Electrical - Switch gear, rough garage, rtu’s
Plumbing - Tub & shower sets & valves
West view - Labor prep tub & shower sets
Week of 5/5/25:
Level #2 insulate/drywall, level #1 - insulate
Sprinkler - Level #3 dry/wet
Level #2 drywall/tape/sand
Garage - roughs ,switch gear
HVAC - RTU’s