3 week look ahead 6/26

Week of 6/23/25:

Insulation level 1 units complete, roof slopes spray foam
Wellesley building inspector : inspect level #1 insulation
Drywall : level #2 hang last 3 units ,start taping level #2, deliver board level #1 & start hanging
Sprinkler : garage dry system ongoing
Plumbing : roof penetrations
HVAC : roof penetrations/ line sets
Tile : level #2 board shower &tub walls w/ fiber board ,set Vineland pans / showers
Herz Rater : level #1
Week of 6/30/25: 

Wellesley building inspector : inspect level #3 rough frame & roof
Insulation: spray foam sloped roofs & flat post VMA penetrations & inspection
Electrical: Run power feeds through roof penetrations
Drywall : hang board level #1 ,tape level#2 & sand ready for paint
Tile : level #2 & #1 prep tubs & shower walls & pans make ready for tile
HVAC: installing rtu’s


Week of 7/7/25 :

Gypcrete level #2
Drywall: Hang /tape level #1 units & prime,paint
Level #2 : start installing cabinets /unit doors / trim / floors
Level #1 : start installing cabinets / unit doors / trim / floors