3 week look ahead 5/12

Week of 5/12/25 :

Sheet metal rough inspection 5/15
Rough frame inspection pending sheet metal
Insulate level #2 & level #1 pending sheet metal inspection and building inspection
Fire Stop - fire caulk level #3,#2,#1
Siding: finishing siding west elevation & front entry, porch ceilings front
Plumbing : rough plumbing inspection : Monday level #3,#2,#1
Sprinkler: level #3 dry complete & on air test, level #2 &#1 wet system fill with water
HVAC : deliver all hvac equipment Tuesday 5/13, crane to roof Wednesday
Electrical: switch gear ongoing, BDA install level #2 &#1
Site: still waiting to confirm water service with Wellesley DPW

Week of 5/19/25:

Insulation / sheet rock pending inspections
Sprinkler : level #3 wet system ongoing
Plumbing: level #3 roof penetrations , garage rough
Gutters & downspouts: deliver last load cabinets
Site: water service pending Wellesley DPW, catch basin, tie in SMH & gas, oil, water separator, down spouts, change order - retaining wall north, subgrade site

Week of 5/26/25:

Sheetrock, tape, mud, sand level #2 ongoing
Insulate level #1
Install RTU’s
Site work ongoing

Next
Next

3 Week look ahead 5/5