3 week look ahead 4/28
Week of 4/28/25:
Level #2  building inspection pending rough plumbing inspection, Insulate/ inspect / sheet rock
Sprinkler - level #3 dry & wet system ongoing
HVAC - pending equipment purchase, delivery mid-May
Plumbing - tub and shower pan sets / valves
Sales - framing 1st & 2nd floor post and closet add ( complete), frame fire place walls add - ongoing
3rd delivery kitchen & bath cabinet delivery 4/30/25 @ 9:00am
Week of 5/5/25:
Level #2 insulate pending plumbing & building rough inspections
Level #1 tub sets & valves ,roof penetrations
Sprinkler - level #3 dry /wet ongoing
Landscaping - front columns stone veneer
Site - cap, flush, pressure test, chlorinate water service
Siding - Fire place walls, siding, trim, porch ceiling bead board
Insulation - Net & insulate level #2, spray
Week of 5/12/25:
Plumbing - level #1 tubs,showers ,valves ,roof penetrations
Coordinate garage plumbing with sprinkler
Insulation: level #2 spray ,sound , insulation inspection,
Level #1 start insulation
Load level #2 Sheetrock pending insulation inspection ,tape & sand
Electrical - switch gear, unit panels
Siding - siding, porch ceiling bead board